Cook County Health Picks Epic for One EHR Across Its Hospitals, Jail Health Service, and Medicaid Plan: What the Contract Shows
Cook County Health (CCH) announced on November 23, 2026 that it has "entered into an agreement with Epic" for its new electronic health record, according to the CCH press release. The system says it cares for more than 600,000 individuals a year through the health system and its health plan. The new platform is meant to span all of it: two hospitals, community health centers, correctional health, public health, and a Medicaid managed care plan.
Most of our readers are not running a public system of this size. The contract documents are still worth a close read. They show how a large public buyer scoped an EHR replacement, how the money is spread across the years, and which IT decisions get made before kickoff. Smaller organizations face the same questions on a smaller budget.
At a glance
- What: CCH selected Epic Systems Corporation through a competitive RFP (contract H25-25-150) to replace its current Oracle Health (formerly Cerner) EMR
- Money: A not-to-exceed ceiling of $102,000,000, spent "as needed," from 10/01/2026 through 09/30/2033, with two five-year renewal options
- Timeline: Implementation kickoff in February 2027, expected to take at least 18 months
- Scope: One standardized platform across all CCH facilities, including public health, health plan services, and clinical research
- For your shop: Inventory interfaces, budget for legacy support overlap, and design role-based access before build starts, not after
What CCH Announced
The press release describes a competitive RFP process and Board of Directors approval "in August." A committee of more than 20 CCH clinical, IT, nursing, and operations leaders served as the RFP review panel. Implementation kickoff is slated for February 2027 and is expected to last at least 18 months. CCH says it is already holding internal meetings and laying the groundwork. The release quotes CEO Dr. Erik Mikaitis and CIO Angela O'Banion.
The release also says patients will get access to MyChart "when fully implemented." It cites Epic's figure of more than 325 million patient records on its network. That number is Epic's, not an independent count.
The release lists the organizations the new platform will serve:
- John H. Stroger Jr. Hospital and Provident Hospital
- More than a dozen community health centers
- The Ruth M. Rothstein CORE Center
- Cermak Health Services, which serves the Cook County Jail and the Juvenile Temporary Detention Center
- The Cook County Department of Public Health
- CountyCare, a Medicaid managed care plan
What the Contract Documents Show
The contract appears as Request #16 in the August 20, 2026 Finance Committee packet. The request is to execute a contract with Epic Systems Corporation of Verona, Wisconsin, under contract number H25-25-150. It is dated 08/12/2026. The executive sponsors are Angela O'Banion (CIO) and Daniel McCormick (Chief Clinical Officer).
Two details are easy to miss in news coverage. First, $102,000,000 is a ceiling, not a price. The packet describes spending "as needed" up to that amount. Second, the term is 84 months, running 10/01/2026 through 09/30/2033, with two five-year renewal options. The packet's own compliance line for the item read "Pending" at the time of the committee meeting. We have not seen the full Board's vote record, so we are relying on the press release's statement that the Board approved the selection in August.
The fiscal-year schedule in the packet shows where the money lands:
| Fiscal year | Not-to-exceed | Relative size |
|---|---|---|
| FY2026 | $2.5M | |
| FY2027 | $28.7M | |
| FY2028 | $13.5M | |
| FY2029 | $13.8M | |
| FY2030 | $13.9M | |
| FY2031 | $11.1M | |
| FY2032 | $11.2M | |
| FY2033 | $7.3M | |
| Total ceiling | $102.0M |
The shape of the curve is the useful part. Spending peaks in FY2027, the build and go-live year, at more than double any later year. It then settles into a run rate of roughly $11 million to $14 million and tapers to $7.3 million by FY2033. If you are planning an EHR replacement of any size, expect the same front-loading. Implementation services, training, and data conversion hit the budget at once, often while you are still paying the outgoing vendor.
One Platform, Many Kinds of Care
The board request describes a "single, standardized platform across all CCH facilities, including Public Health, Health Plan Services, and Clinical Research." The RFP listing, titled "Electronic Health Record (EHR) Solution," also calls for a single standardized instance across all CCH facilities. Bids were due 01/23/26, and the listing notes that Addenda #3 and #4 were posted. The listing shows a prebid date of 12/08/25, but the listing is flagged as updated, and other sources we checked point to a different date, so treat that date as unconfirmed. The solicitation itself was hosted on CCH's Bonfire procurement portal.
Per the board request, the contract scope covers revenue and patient access, core clinical systems and mobility, specialty, departmental, and ancillary systems, population health, analytics, patient engagement and mobility, and interoperability. Epic staff will handle planning, configuration, testing, training, data conversion, and deployment as part of related implementation services. The request also mentions using emerging technologies, including AI, as they mature. If AI features are on your roadmap, Epic's own plans are moving quickly; see our coverage of Epic's planned inbound MCP access for outside AI agents.
A single instance is a deliberate choice, and it is not a small one. Organizations that start with multiple instances often spend years consolidating later. Our report on Endeavor Health folding three Epic instances into one shows what that cleanup looks like. CCH is choosing to absorb that complexity up front, across settings as different as a jail clinic, a public health department, and a Medicaid plan.
What Is Being Replaced
The press release does not name the outgoing system. CCH's own April 2024 procurement packet does. It describes "Oracle Corporation (formerly Cerner)" as the current CCH EMR system of record, under a sole-source support and maintenance contract. That packet carried a $109,992,286.21 request to amend, extend, and increase the Oracle agreement.
We have not confirmed when the current Oracle Health support agreement ends. It matters, because an 18-month-plus implementation that kicks off in February 2027 cannot go live before late 2028 at the earliest. The outgoing system has to stay fully supported, patched, and staffed until cutover and through any read-only archive period after it. That overlap is a line item many smaller organizations forget. For a broader comparison of the two vendors from a smaller organization's perspective, see Epic vs. Oracle Health for Small and Rural Organizations.
What IT Teams Should Take From This
You do not need a $102 million ceiling to learn from this procurement. The work below applies whether you run IT for a large public system or a small clinic considering a move to a hosted EHR.
Build the interface inventory now
Every HL7 feed, FHIR endpoint, flat-file export, and point-to-point integration on the current system has to be rebuilt, retired, or replaced. Interoperability is a named scope item in CCH's contract. Start with a spreadsheet: source system, destination, message type, interface engine route, owner, and whether the receiving party will still exist after cutover. Lab, pharmacy, imaging, billing clearinghouse, and state reporting feeds are the usual long poles. If FHIR interfaces are part of your list, our piece on the HL7 and SNOMED International partnership covers terminology changes worth tracking.
Decide what data actually converts
Data conversion is in Epic's scope for CCH, but someone at the customer still decides what converts discretely, what moves as documents, and what stays in a legacy archive. Those decisions drive cost, timeline, and how clinicians experience the first months after go-live. Make them with clinical leadership, not just IT.
Design access control for every setting before build
A single instance shared by acute care, correctional health, public health, a health plan, and research puts heavy weight on role-based access design. The HIPAA Security Rule's access control standard at 45 CFR 164.312(a)(1) requires technical policies and procedures that allow access to electronic protected health information only to persons or software programs that have been granted access rights. Unique user identification at 164.312(a)(2)(i) is a Required implementation specification. The audit controls standard at 164.312(b) requires mechanisms that record and examine activity in systems containing ePHI. In practice, that means mapping every job role in every setting to a security class before configuration, and agreeing on who reviews access logs once the system is live.
Protect data in motion and during migration
Conversion jobs and new interfaces move large volumes of ePHI. The integrity standard at 164.312(c)(1) requires policies and procedures to protect ePHI from improper alteration or destruction. The transmission security standard at 164.312(e)(1) requires measures to guard against unauthorized access to ePHI sent over a network. The related implementation specifications for authenticating ePHI at 164.312(c)(2), and for transmission integrity controls and encryption at 164.312(e)(2)(i) and (ii), are Addressable. Addressable does not mean optional: you implement the specification, or you document why it is not reasonable and appropriate and what equivalent measure you use instead. For conversion work, reconciling record counts and checksums between source and target is a practical way to show integrity was preserved.
Plan for the cutover weekend and the downtime that surrounds it
Every EHR go-live includes planned downtime, and usually some unplanned downtime too. Paper procedures, read-only access to the legacy system, and a tested recovery plan should be in place before cutover, not written during it. Our disaster recovery planning guide covers the basics for smaller organizations.
Copy the governance model, scaled down
CCH used a review panel of more than 20 clinical, IT, nursing, and operations leaders. A small clinic does not need 20 people, but it does need the same mix: someone who sees patients, someone who bills, someone who runs the front desk, and someone in IT. Vendor demos look very different to each of them, and a selection made by IT alone tends to surface its problems at go-live.
What We Do Not Know Yet
Several details are not public in the documents we reviewed. These include the go-live wave plan and sequencing across facilities, the hosting model, and the full inventory of interfaces and third-party applications to be retained or retired. The total cost of ownership beyond Epic's contract ceiling is also unknown; internal staff, hardware, the Oracle Health overlap, and backfill for training time are not in that $102 million figure. We also have not seen how CCH plans to handle workflows specific to Cermak Health Services in the jail and juvenile detention settings. We will follow up as the February 2027 kickoff approaches.
This article is for informational purposes only and does not constitute legal or compliance advice. Covered entities and business associates should consult qualified legal counsel or compliance professionals before making decisions pertaining to HIPAA or IT infrastructure.
Sources
- Cook County Health, "Cook County Health Selects Epic as New Electronic Health Records System" (press release, November 23, 2026): cookcountyhealth.org
- Cook County Health, Finance Committee Proposed Contracts and Procurement Items, August 20, 2026 (Request #16, Epic Systems Corporation, H25-25-150): cookcountyhealth.org (PDF)
- Cook County Health, Proposed Contracts and Procurement Items, April 19, 2024 (Oracle Corporation, formerly Cerner): Documenters (PDF)
- IllinoisBids, "Electronic Health Record (EHR) Solution" RFP listing, Cook County Health and Hospitals System: illinoisbids.com
- Cook County Health Bonfire procurement portal, Opportunity 210078: cookcountyhealth.bonfirehub.com
- Electronic Code of Federal Regulations, 45 CFR Part 164 (Security and Privacy), including 164.312 Technical safeguards: ecfr.gov